






|

All links on this page will open a flickr.com slideshow in a new window. Once the slideshow starts click on the
picture to turn on/turn off descriptions. To return to HiStar Ranch at any time simply close the Flickr window.
Beginning July 5th some slideshows will include videos which can be played by clicking on the Play Video link that is
visible while descriptions are turned on. To return to the slideshow close the video window.
If you wish titles and descriptions to be displayed by default, click on the Options button in the bottom right corner
of the slideshow screen, select "Always show titles and descriptions", and SAVE.
SketchUp 3D Model based on Final Construction Drawings
3D Model - Exterior Views
3D Model - Interior Views
Construction Photos
Construction Begins (12/25/2007)
Our first visit to the home site since the Construction Loan was finalized occurred on Christmas Day 2007. We were
early in the construction process, but the builder had put in the temporary driveway as required by the subdivision's
Architectural Control Committee and had begun staking out the footprint of the house and garage.
Foundation Excavation (12/30/2007)
On Sunday, 5 days after our Christmas Day visit, we discovered that the builder had brought out a tractor and had
begun excavating the area designated by the orange survey flags.
Foundation Filling (1/22/2008)
The third week of January 2008 was our next visit to the construction site since New Years Day. The entire week was
cold, rainy and foggy. Temperatures were in the upper 30s and the atmosphere was dense with moisture. But work
continued at the site as numerous dump trucks of foundation fill were delivered.
Foundation Forms Complete (2/21/2008)
On our last visit in January, we knew that we would be back to the building site in about a month. Our timing was
good -- the foundation preparation were almost complete and we would be there to witness the pouring of the
foundation.
Milestone #1 - Pouring Foundation (2/25/2008)
It was a beautiful day for the first major milestone of construction. The skies were clear and high. The temperature
at 8:00 was about 50°F and warming with low humidity and a steady breeze.
The foundation pouring was scheduled to start early this Monday morning around 6:00 a.m. We arrived at Whitewater
Springs around 8:00 a.m. after having passed 7 concrete trucks from our pour on our way.
Framing Begins (3/09/2008)
After the foundation was poured on 2/25/08, the framing of the first floor began about 10 days later during the first
week of March 2008.
Second Floor Framing (3/27/2008)
Second floor trusses have been installed and the second floor has been framed. Roofing trusses have also been
installed.
Going Upstairs (3/29/2008)
Since the builder had told us that the stairs to the second floor would be in place, we visited again on Saturday to
see our views from the second floor. But the weather did not let that happen as it was very cool and foggy.
Exterior Sheathing Installed (4/10/2008)
Returning two weeks after our last visit on 3/29, we saw that the framers had been busy putting up the exterior
sheathing on the outside walls and working on the roofs and eaves.
Sunrise at Whitewater Springs (4/12/2008)
We got up very early on Saturday morning and left Cedar Park around 6:00 a.m. We arrived at Whitewater Springs 35
minutes later -- before sunrise. The sky was lightening when we got to the construction site and we were able to
watch the sunrise from the Master Bedroom window.
Sheathing and Soffits (4/14/2008)
This was our last visit for this trip from Houston and the framers were still busy installing the exterior sheathing
and soffits.
Windows and Roofs (4/23/2008)
We were away for a week, but the house in today's visit was really beginning to look like a house. The windows were
in, the roofs were on and the interior had the bracing timbers removed.
Exterior Paint Sample (4/26/2008)
After getting exterior paint selections from our architect project manager, the builder had the painter paint some
samples on the back of the garage for our review.
Siding and Stone Samples (4/28/2008)
While the framers were continuing their progress with the installation of the siding, the builder went to the stone
quarry in Lometa, TX, today and picked up stones samples. These were laid on the ground by the exterior paint samples
and the combination looked great.
Electrical AC Rough-Ins (5/23/2008)
It was almost a month before we were able to visit the building site again (we were delayed in Houston preparing to
sell our house there). During the time that we were absent, the mechanical rough-ins had been occurring - electrical,
plumbing and HVAC. These rough-ins continued for a few more weeks. Also, some additional interior framing had
occurred - stairway, screened porch and pocket doors in the Master Bathroom.
Interior Framing (6/1/2008)
During the past week as we were in Houston taking care of the sale of our house there, mechanical rough-ins continued.
But the biggest noticeable difference was that some additional framing in the interior had occurred -- decking for the
bathtub, shower benches, and a railing at the top of the stairs.
Cornerstone (6/2/2008)
To commemorate the building of this house, we had Southwest Monuments & Signs Company in Cedar Park prepare an
appropriate cornerstone of Cordova Cream limestone. This cornerstone will be installed on the Front Entry Porch.
Exterior Primer (6/15/2008)
While the mechanical installations were being handled inside the new house, the painter, Jorge, was preparing the
exterior for painting by caulking the lap siding. Jorge sprayed the exterior with Kelly-Moore AncryShield primer in
preparation for painting the selected Sherwin-Williams paints.
Exterior Paint, Fire Sprinkler, Lightning Rods
(6/21/2008)
Things began happening quickly during the third week in June. On this visit we saw that the exterior painting had
started, the lightning protection system had been installed and the fire sprinkler system had been installed.
Metal Siding (6/25/2008)
After meeting with our builder, Neal, at the local cabinet maker's shop in the morning, we made the trip out to the
building site in the afternoon. A crew installing the corrugated metal siding was there and had begun installing the
siding on the back side of the Garage.
Metal Siding Continues (6/29/2008)
The weekend visit to the construction site with the family showed that about half of the house has been completed with
corrugated metal siding.
More Metal Siding (7/05/2008)
The installation of the metal siding on the exterior continued through the Fourth of July week. Still not done was an
area on the front entry porch and on the rear porches.
Video: Various Looks at the House (7/05/2008)
On this Independence Day weekend, we created some video looks at the progress of the construction. The current phase
of installing the corrugated metal (Galvalume) continued.
Fireplaces, Low-voltage Wiring (7/11/2008)
Friday's visit revealed that the Living Room fireplace box and the Screened Porch fireplace box have been temporarily
installed.
Rainwater Collection (7/13/2008)
Sunday's visit revealed that the builder had been busy working on Saturday, 7/12 (he admitted that he put in 14-15
hours that day). With the use of a Bobcat tractor, Neal moved dirt/rock fill up to the foundation to increase the
grade to accommodate the rainwater collections system.
Videos: Activities-Week of 7/7/2008
(7/13/2008)
The week of 7/7/08 was a very busy week at the construction site -- roofing was installed, low-voltage wiring was
strung, plumbing was completed and rainwater collection piping began.
Roofing (7/14/2008)
The roofing of the house began today. The roof is Galvalume metal sheets. The installers began installing around
10:30 a.m. and by 3:00 p.m. had completed the rear section of the upper roof. Temperature today was about 105
degrees, so it must have been like working on a stove top.
Video: Roofing, Low-voltage (7/14/2008)
Construction activities today included the roofing of the house with Galvalume sheets, the installation of low-voltage
wiring and the installation of the conduit for the rainwater collection system.
More Roofing, Painting (7/15/2008)
The roofing installation continued today on another hot triple-digit day. The week continued to be a busy one at the
construction site as the painter was painting the porches, the low-voltage installers were there in addition to the
plumbers.
Roofing, Painting Wrapping Up (7/17/2008)
The busy week continued as the roofing, painting, plumbing and low-voltage wiring installation continued.
Roof Complete, Trenching Started (7/22/2008)
A weekend visit after a very busy week showed that the roofing had been completed. The builder had stuccoed the
foundation on the rear of the house and had dug a trench for the utilities from the service area at the street to the
house.
Insulation Begins (8/6/2008)
After not much activity over the past 2 week, insulation of the house began today, Wednesday 8/6/2008. The house
proper will receive sprayed-on polyurethane foam insulation. The garage as well as the ceilings of the two porches
will be insulated with standard batt insulation.
Video: Insulation Installation (8/6/2008)
This set contains videos of the spray foam insulation activities on Wednesday, 8/6/2008.
Insulation Complete (8/9/2008)
The trip to the construction site on Saturday, 8/9/08, showed us that the insulating contractor had completed their
job on Friday. All exterior walls and the underside of the roofs had been sprayed with the polyurethane foam.
Hanging Drywall - Day 1 (8/15/2008)
The hanging of the drywall board began today, Friday, 8/15/08. The crew arrived early and by the time we arrived at
10:30, most of the second floor had been done and about half of the first floor was complete.
Video: Hanging Drywall - Day 1 (8/15/2008)
This set contains videos of the drywall installation that began on 8/15/08.
Hanging Drywall - Day 2 (8/16/2008)
The drywall installers were again on site for Day 2 on Saturday, 8/16/08. They had arrived the day before on Friday,
8/15/08, to begin installing the drywall to the framed walls.
Taping/Floating Drywall (8/21/2008)
The drywall installers were back on 8/21/08 to tape and float the drywall that they installed the previous weekend. A
summer afternoon thunder shower came rumbling through while they were there.
Video: Taping/Floating Drywall (8/21/2008)
This set contains videos taken during the day Thursday, 8/21/08, when the drywall installers were back to tape and
float the drywall that they installed the previous weekend.
Drywall Floating Complete (8/23/2008)
A weekend visit to the job site revealed that the drywall installers have completed the floating of the walls and
ceilings. They returned the following week to sand the walls/ceilings smooth before spraying texture.
Texture Walls (8/28/2008)
A week after the drywall was taped and floated, the contractors were back to spray wall texture. They had returned
earlier this week to sand the walls/ceiling smooth before spraying the texture.
Video: Texture Walls (8/28/2008)
This set contains video that were taken the day that the drywall installers were spraying texture on the walls.
Septic Construction (8/28/2008)
While drywall texturing was proceeding inside, Alcam Services employees arrived to begin the installation of the
septic system. They arrived with a backhoe to start the trenching and digging.
Video: Septic Construction (8/28/2008)
This set includes videos of the Alcam Services backhoe operator arriving, removing cedar trees and beginning to dig
the aerobic septic system.
Priming Walls, Trimming Prep, Septic
Construction, Flooring Samples (8/30/2008)
Interior detailing began this week -- Door frames were delivered; Walls were sprayed with primer; Custom trim was cut.
The builder also provided us with mesquite flooring samples.
Trimming Prep, Septic Construction, Sandstone
Delivery (9/3/2008)
A visit to the construction site after the Labor Day weekend holiday (Hurricane Gustav had just hit Louisiana, but no
impact here), the builder continued to prepare the custom trim for the doors, windows and baseboards. The septic
installer was still digging the hole for the septic system through solid limestone. Also the first load of Lometa
sandstone had been delivered.
Video: Trimming Prep, Septic Construction
(9/3/2008)
This set contains videos of the builder and his employees preparing the custom trim and of the septic installer
digging a hole in the solid limestone for the septic system.
Trimming Install, Septic Install (9/7/2008)
We visited the construction site on Sunday, 9/7/08, after a 4-day business trip to Houston. During our absence, the
builder was busy installing the trim and shelves that had been prepared last week. The door frames had been installed
and trim around the windows and doors had begun. Also the septic system installer had completed preparing the hole
and had installed the septic tanks.
Video: Septic Install (9/7/2008)
The video in this set is a quick look around of the septic system that was installed the previous week.
Septic Completion (9/10/2008)
The basics of the aerobic septic system was installed and the Burnet Country engineer came onsite to inspect the
system before it is covered up.
Video: Septic Completion (9/10/2008)
The video in this set was taken from the Open Porch of the septic system and the septic spray field.
Stone Wall Mock-up (9/14/2008)
Per the building specifications, the builder is required to erect a mock-up of the stone exterior for review by the
owners and the architects before proceeding. This set is photos of the mock-up of the Autumn Blend sandstone from
Kirby Stone Co. in Lometa, Texas. We requested a color composition of 60% tan, 30% brown and 10% rust.
Interior Painting - Day 1 (9/16/2008)
The painting of the interior walls began today, Tuesday, 9/16/08.
Interior Painting - Day 2 (9/17/2008)
Painters continued with the painting of the accent walls.
Interior Painting - Day 3 (9/19/2008)
After painting the interior walls, the painters taped off the walls to allow for painting the door and window trims.
On Day 3, the trims were painted with primer and sanded before they are sprayed with enamel paint.
Interior Painting - Day 4 (9/22/2008)
After taping the walls around the windows and doors, all interior trim was painted with Sherwin Williams "Softer Tan"
enamel paint.
Stained Concrete (9/23/2008)
Today, the builder stained the floors of the Front Entry Porch, Screened Porch and Open Porch with Antique Amber
concrete stain.
Exterior Stone - Day 1 (9/24/2008)
Five stone workers arrived today, Thursday, 9/24/08. Three were stone masons and the other two assisted by mixing
mortar and retrieving stone. They began laying the stone on the exterior, starting with the lower portions of the
garage first.
Video: Exterior Stone - Day 1 (9/24/2008)
Video activities on Day 1 of stone work.
Exterior Stone - Day 2 (9/25/2008)
Laying of the sandstone exterior continued for the second day. And the builder started preparing the floor inside for
wood flooring.
Video: Exterior Stone - Day 2 (9/25/2008)
Video activities on Day 2 of stone work.
Exterior Stone - Day 3 (9/26/2008)
Great progress on the sandstone exterior today. All lower sections of the walls were completed and the masons began
building the stone columns. And while the masons were working outside, the builder was working inside laying sleeper
boards and plywood in preparation for the mesquite solid wood flooring.
|